Pressure Reducing Valve Station Replacement

Vicinity Map

Location: Various locations, see vicinity map

Project Phase: Construction

Estimated Timeline: Construction began in July 2018 with completion expected in June 2019.

  • NE 28th St & 173rd Ct NE: Construction on PRV Station 23 is 95% complete. Landscaping restoration will be completed in Spring 2019.
     
  • NE 55th Way & 160th Ave NE: Construction at PRV Station 36 is 95% complete. Property restoration will be completed in January 2019.
     
  • NE 40th St & 162nd Ave NE: Construction at PRV Station 14 is 90% complete and will be completed in January 2019.
  •  
  • NE 40th St & Bel-Red Road: Construction at PRV Station 15 is ongoing and will be completed in February 2019.
  •  
  • NE 59th Way & 158th Way NE: Construction at PRV Station 37 will begin late in December 2018 and be completed in February 2019.
  •  
  • NE 65th St & NE 66th Pl: Construction at PRV Station 38 will begin late in January 2019 and be completed in March 2019. NE 65th St will be closed west of NE 66th Pl from 9:00 a.m. to 3:00 p.m. daily. Please follow detour signage.
Contact: Eric Dawson, 425-556-2867

Page Last Updated: 01/18/19

Description:
The City uses approximately 84 pressure reducing valve (PRV) stations to manage water pressure in the City’s distribution system. Many of these PRV stations were built in the 1960s and 1970s and are in need of refurbishment. City staff inspected and evaluated all of the Redmond's PRV stations and generated a list of those needing rehabilitation or replacement. These stations no longer meet City standards due to pipe corrosion, age, type of materials used, and environmental conditions. Corrosion is the main cause of degradation, but other issues include vault drainage and safe access.

This project will abandon and replace 10 PRV stations throughout Redmond. The construction will provide for installation of new vaults, valves, piping and restoration of all street, sidewalk and landscape within the limits of construction.