Redmond Way Stormwater Trunk/Water Quality Facility
Location: Various
Current Project Activities: Project under construction along BNSF right-of-way and downtown streets.
Project Phase: In Construction
Estimated Timeline: Construction expected to continue until Spring 2012
Project Manager: Mike Haley, 425-556-2843
Description: Redmond Way Stormwater Trunk will convey all stormwater runoff directly from the east end of downtown Redmond to the Sammamish River. The Redmond Way Stormwater Quality Facility will collect low flows from the stormwater trunk and provide water quality treatment to the runoff prior to discharge to the River.
April 2011 Newsletter