Study Schedule
The Downtown East/West Corridor Study is now complete.
Following is the study schedule through the first quarter of 2009.  
 

Task

Timing

Presentation to Historical Society   Apr 8, 2008
Presentation to Pedestrian/Bicycle Advisory Committee   Apr 14, 2008
Presentation to Chamber of Commerce/Government Affairs   Apr 15, 2008
Meeting with Washington State Department of Transportation: Discussion of traffic analysis   Apr 28, 2008
Presentation to Chamber of Commerce interested parties   Apr 30, 2008
Presentation to Planning Commission   Apr 30, 2008
Presentation to Parks and Trails Commission   May 1, 2008
Planning/Public Works Committee   May 8, 2008
City Council - Channelization Plan Decision   May 13, 2008
Public Meeting #1   June 19, 2008
Property Owner Meetings   Aug - Sept 2008
Pedestrian and Bicycle Advisory Committee   Sept 8, 2008
Planning Commission   Sept 24, 2008
Historical Society   Oct 7, 2008
Chamber of Commerce Government Affairs Committee   Oct 14, 2008
City Council Planning and Public Works Committee   Oct 14, 2008
City Council - Corridor Plan, Implementation Plan, BNSF Corridor   Oct 21, 2008
Parks and Trails Commission   Nov 6, 2008
Public Meeting #2   Nov 17, 2008
City Council - Project Update   Feb 24, 2009
Conditional letter of support received from
Washington State Department of Transportation
Mar 17, 2009
City Council - Approved Downtown East/West Corridor Study
Master Plan and Implementation Strategy
  Mar 17, 2009
City Council - Approved amendments to the 2009 - 2014
6-Year Transportation Improvement Program
  Mar 17, 2009
Downtown East/West Corridor Study is complete   Apr 2009